Centrica is seeking urgent talks with the Prime Minister to save up to 400 jobs at Britain's largest gas storage site. The British Gas owner says it plans to shut the North Sea facility next spring unless ministers agree to long-term financial support. The imm
Illustrative imageCentrica is seeking urgent talks with the Prime Minister to save up to 400 jobs at Britain's largest gas storage site.
The British Gas owner says it plans to shut the North Sea facility next spring unless ministers agree to long-term financial support.
The immediate setback came when the Government rejected a deal to use the Rough site for gas storage this winter.
In a leaked memo to staff on Friday, Centrica chief executive Chris O'Shea said Energy Secretary Miatta Fahnbulleh had confirmed the decision.
He told workers the company was "doing everything we can to save your jobs".
Rough's operating permission expires on April 30, 2027.
The North Sea Transition Authority has already approved plans to stop operations, and Centrica has indicated it will let its existing licence expire.
Ministers are still considering responses to a consultation that closed in February. Mr O'Shea said the company was "extremely disappointed by the further delay".
"She has also said the department needs more time to work through the consultation responses, and that its full response will now come at some point next year," he wrote.
It wants ministers to bring the site into a Government scheme that gives storage projects a minimum level of revenue and caps how much they can earn.
"Since then, world events have only made the case for Rough stronger," Mr O'Shea wrote.
As Middle East conflict squeezed global gas supplies, the company began discussions with the Government in April about deploying Rough as a short-term strategic reserve.
Under the proposal, gas would have been pumped into storage over the summer months and held for release this winter, but only at the Government's request.
The warning arrives at a particularly sensitive moment for Britain's energy security.
The conflicts in Ukraine and Iran have heightened concerns about supply, while the cost-of-living crisis continues to weigh on households.
Rough sits 18 miles off the East Yorkshire coast. The facility supports around 100 jobs at the site and a further 350 in the supply chain.
Mr O'Shea said Centrica would hold talks with the trade union Unite about what the decision means for workers.
The Government rejected the deal as a cold snap put pressure on Britain's electricity supplies.
On Friday, the grid operator asked power suppliers to prepare extra back-up generation for an unprecedented fourth day in a row. Planned maintenance on the network coincided with the cold weather.
A spokesperson for the Department for Energy Security and Net Zero said: "National Gas' Winter Outlook confirms we have enough gas to meet demand this coming winter - only five per cent of our supply came from storage last winter."
The department said it had set out plans to keep gas supplies secure, including options for financial support for the storage sector, while protecting consumers from unnecessary costs.
"A decision is now needed, and every month of delay narrows the options available," he wrote.